August 2026 Progress Update
Construction Progress Milestones
Building with transparency
Construction Progress
Overall project progress
12%
According to our internal inspection conducted on 31-08-2026, the overall project's progress is 12%
Project Timeline 2026
At Misa Property Developers, we are committed to keeping our investors informed at every stage of construction. This timeline shares monthly progress updates, completed works, key milestones and site photographs for Misa Luxe 1. Our focus remains on quality, transparency and long-term value as the project moves forward.
2026 August
Construction Progress Milestones
1. Diaphragm wall construction continued during August, with 21 of the revised total of 28 reinforcement cages completed, installed, and cast.
2. Reinforcement cage fabrication, panel installation, concreting, and associated site activities continued in accordance with the construction programme.
3. Following completion of the diaphragm wall works, capping beam construction is scheduled to commence, with PDA testing also planned as part of the next phase of works.