Latest Update for month of May
Construction Progress Milestones
A Major milestone achieved
Construction Progress
Overall project progress
8%
According to our internal inspection* conducted on 31-05-2026, the overall project's progress is 8%
Project Timeline 2026
At Misa Property Developers, we understand that true value in real estate comes from quality that endures. Too often, properties are developed quickly with a focus on quantity over lasting appeal, leading to early depreciation and diminished returns for investors.
2026 May
Construction Progress Milestones
1. Diaphragm wall construction is accelerating, with 6 out of 32 reinforcement cages now successfully installed and cast, steadily advancing the formation of the structural perimeter wall.
2. Strategic planning for the three-level underground basement has been successfully finalized, fully establishing the comprehensive methodologies for deep excavation, structural coordination, and long-term stability.
3. MEP coordination remains tightly integrated with the ongoing diaphragm wall works, ensuring all service provisions and sleeve penetrations are accurately positioned within each cage layout prior to installation.
4. Foundation engineering and site execution workflows are fully synchronized, driving increased operational efficiency, precision, and adherence to the highest quality standards as the basement phase gains momentum.