September 2026 Progress Update
Construction Progress Milestones
Building with transparency
Construction Progress
Overall project progress
15%
According to our internal inspection conducted on 30-09-2026, the overall project's progress is 15%
Project Timeline 2026
At Misa Property Developers, we are committed to keeping our investors informed at every stage of construction. This timeline shares monthly progress updates, completed works, key milestones and site photographs for Misa Luxe 1. Our focus remains on quality, transparency and long-term value as the project moves forward.
2026 September
Construction Progress Milestones
1. Diaphragm wall construction was completed during September, with all 28 reinforcement cages completed, installed, and cast.
2. Reinforcement cage fabrication, panel installation, concreting, and associated diaphragm wall activities were completed in accordance with the construction programme.
3. San Piling, the diaphragm wall contractor, was also engaged to carry out the subsequent excavation works.
4. Following completion of the diaphragm wall works, capping beam construction and PDA testing are scheduled to be carried out prior to the commencement of excavation works.